California Or-Equal Requirements

by Bernard S. Kamine

(versions of this article appeared in the ECA Magazine, January 2004, p. 17 and the Los Angeles Daily  Journal, December 30, 2003, p. 7)

                        California public agencies must allow public works contractors to provide an “equal” to materials, products, things, or services specified in the contract documents.  This assures the public gets the lowest prices, prevents one product from locking up a project, encourages competition among functionally equal products and prevents favoritism and corruption.

The Public Contract Code lays out the requirement and the procedures for implementation.  It also describes exceptional situations when the “or-equal” requirement may not apply.  Case law explains what is and is not an equal.

The “or-equal” requirement has been California law since at least 1961 when former Gov. Code § 4380 was added.  The current statute is Public Contract Code § 3400 (almost identical language also appears in the State Contract Act, Public Contract Code § 10129).  It prohibits any public works contract from limiting “the bidding, directly or indirectly, to any one specific concern, or … calling for a designated material, product, thing, or service by specific brand or trade name unless the specification is followed by the words ‘or equal’ so that bidders may furnish any equal material, product, thing, or service.”  The requirement is applicable to every “agency of the state … political subdivision, municipal corporation, or district … [and] to any public officer or person charged with the letting of contracts for the construction, alteration, or repair of public works.”

The requirement has been incorporated into the two most widely used standard public works contracts, Caltrans’ Standard Specifications (California Department of Transportation, 1999) section 6-1.05, and Standard Specifications for Public Works Construction (BNi Publications, Inc., 2003) section 4-1.6.

The goals of the “or-equal” requirement are “to widen the area of competition, and to bar local procurement officials from choosing a particular source either out of favoritism or because of an honest preference.”  Jack Stone Co. v. United States, 344 F.2d 370, 373-74 (Ct. Cl.1965).  These goals are essentially the same as the reasons for requiring competitive bidding: “to guard against favoritism, improvidence, extravagance, fraud and corruption; to prevent the waste of public funds; and to obtain the best economic result for the public.” Graydon v. Pasadena Redevelopment Agency, 104 CA 3d 631, 636 (1980).

When these goals cannot be achieved, courts will not enforce the competitive bidding or “or-equal” requirement.  In these situations, an agency may specify a particular product or a “sole source.”

Public Contract Code § 3400(b) now spells out those situations.  The statute allows sole sourcing for four reasons: (1) to conduct a field test or experiment of the product, (2) to match existing products in use on the particular public work, (3) to obtain a product that is only available from one source, and (4) to respond to an emergency.

However, before an agency can resort to sole sourcing for one of these reasons, the awarding authority or its designee (e.g., the city engineer) must make a finding that one of the four reasons applies.  Further, that finding must be described in the invitation for bids or request for proposals.

So, bidders should check invitations for bids and requests for proposals for a justification for the sole sourcing of any material, product, thing, or service specified in contract documents.  If no justification appears, the agency must accept equals.

The 2003 amendment to the “or-equal” law explains that the four reasons for allowing sole sourcing “are intended to codify, and not to change the application of, existing California case law.” 2003 Cal.Stats. Chapter 233, Section 3.  That case law involves competitive bidding requirements, and allows exceptions to competitive bidding “where it has appeared that competitive bidding would be incongruous or would not result in any advantage to the public entity in efforts to contract for the greatest public benefit. … [for example, where] the governmental entity has entered into contracts for personal services depending upon a peculiar skill or ability [citations]; contracts for the purchase of patented products [citations]; contracts for the provision of services or the construction of public improvements by a government regulated monopoly [citations]; contracts for experimental or unique products and/or services [citations]; and actions or contracts for the acquisition or disposition of property for a particular use and with a special value to one person [citations].”  Graydon v. Pasadena Redevelopment Agency, 104 CA 3d 631, 636-37 (1980).

The project specifications are supposed to call out the time period, before or after award, during which the contractor must submit “data substantiating a request for a substitution of ‘an equal’ item, [and,] [i]f no time period is specified, data may be submitted any time within 35 days after the award of the contract”.  Public Contract Code § 3400(a).

Obviously, 35 days is not sufficient time on large or complex projects, so the agency should specify more time, maybe even staggering several deadlines to correspond to the appearance of various subcontractors on the project.

Nothing prevents an agency from accepting and considering or-equal submittals after the deadline.  An agency should do so when the contractor based its bid on the or-equal price, because the agency is getting the benefit of that lower price.

Although the statute allows an agency to demand or-equal submittals before award of the contract, doing so should be avoided.  It raises the specter of award manipulation to avoid a legitimate or-equal – which defeats the express purposes of both the or-equal requirement and the competitive bidding laws.

Case law establishes the criteria for determining when a product is equal to what was specified.  Functionality is the basic test of equality.  State and federal courts have no difficulty enforcing the “or-equal” requirement, usually by making the agency pay the difference in cost between the specified product that the contractor was compelled to provide and the equal product that the contractor offered to provide.

For example, in Argo Construction Co. v. County of Los Angeles, 271 CA2d 54 (1969), the contractor sued the county for the difference in cost between the movable metal partitions which the contractor had proposed as an equal and the specified partitions which the county made him install.  The proposed partitions did not have single line joints and did not extend all the way to the floor with continuous thickness as did the specified brand.  The county claimed that “it, just as any other owner, is entitled to insist that the construction satisfy its aesthetic requirements.”

But the Argo court rejected that argument and awarded damages to the contractor, holding that “if aesthetics were permitted to rule the choice, [what is now Pub. Cont. Code § 3400] would in most cases be dead letter.”  The court ordered the county to pay the difference between the specified product and the offered equal.

Another example is Sherwin Electric Service v. United States, 436 F2d 992 (Ct. Cl. 1971), where the contract involved an emergency electrical system at the Veterans Hospital in Fresno.  Only one manufacturer’s automatic transfer switch could meet the specifications.  The government had refused to permit the contractor to use the product which the contractor had submitted as an equal to the specified switch.

The court first held that the use of such a proprietary specification amounts to the same thing as specifying that product by its brand name.  Then the court stated the legal test for determining what is an equal:  “Whether the substitute functions as well, in all essential respects, as the specified equipment.”

After analyzing the two types of switches, the court concluded that the switch proposed by the contractor should have been accepted as an equal, as it “would have proved as effective and as durable in the performance of the contract work as the ASCO switch described in the specifications.”  Again, the government was ordered to pay the difference between the specified product and the offered equal.

KAMINE LAW PC
REPRESENTING CONTRACTORS, SUPPLIERS, SURETIES AND OWNERS SINCE 1976
phone:213/972-0119. fax: 213/972-0005. website: www.KamineConstructionLaw.com

DISCLAIMER: This article is offered without charge; please pass it on to others who may find it useful. Providing this article in no way creates an attorney-client relationship between any reader and Kamine Law PC or the author(s). WARNING: Changes in the law may affect the accuracy of this article, and the information here may not be applicable to your particular situation. You should contact an attorney before using this information.